The Harar Water Supply and Sanitation Project took more than 36 months to be completed and thus did not adhere to the original closing date but faced an enormous delay and caused high cost overruns. Due to the failure in completing the project within the agreed time target, there were severe problems in the socioeconomic development of the areas affected. In the view of the above, there is a need for a better understanding of the causes and effects of the delays in the construction of the Harar Water Supply and Sanitation Project.
This study assesses the causes for the delay of the project. To achieve this, a detailed literature review will help to examine previous studies in the research area and identify the major causes and effects of delays in similar project in other countries. I will also review the full report of the Harar water supply construction project. An interview survey will furthermore help to identify the factors that contributed to the delay.
Table of Contents
Introduction
General Objective
Specific Objective
Significance of the study
Scope of the study
Limitations of the study
Methodology
LITERATURE
Previous studies
Delays construction project
Causes of Delay construction project
Overview of Harar Water Supply construction project
Location of the Project and Duration
Location of the Project
Duration of the Project
Budget of the project
Objective of the project
The major component of the project
Purpose of the project
Project activity
Assessment of the project achievement
FINDING
The causes of delay construction Project
Implementation challenges
Project design complexity
The effect of delay in construction project
Action taken to solve the problem of delayin project
CONCLUSIONSAND RECOMMENDATIONS
Conclusions
Recommendations
Research Objectives and Focus
This study aims to assess and identify the underlying causes of construction delays in the Harar Water Supply and Sanitation Project, while examining the resulting impacts and potential solutions to mitigate such implementation challenges.
- Identification of root causes for construction delays in urban water supply projects.
- Evaluation of the socio-economic and project-specific effects of these delays.
- Assessment of project management strategies and implementation challenges, such as procurement and design changes.
- Review of institutional capacity and bureaucratic factors affecting project timelines.
Excerpt from the Book
Implementation challenges
The Borrower monitored the implementation of the Project through the Executing Agency (EA)[List the main Ministries, Project Implementation Units, Agencies and civil society organizations responsible for implementing project activities], the Project Management Unit (PMU) and the Water Resources Development Fund (WRDF) which is responsible for managing and monitoring the loan part of the project.
The Executing Agency was the MoWE, the project staffs were stationed in Addis Ababa and managed the project through the Coordination Office located in Harar which created gaps in closely managing the project. Also the project was understaffed as it consisted only of the Project Manager, a Water Supply and Sanitation Engineer and an Accountant. All these, among others things, contributed to delays in project completion. Some of implementation challenges are;
(i) Frequent design changes,
(ii) lack of close supervision of the consultants and failure by the consultants to closely monitor the contracts,
(iii) Slow physical progress as result of failure to timely commence and complete physical activities and utilize the allocated budget as planned, and
(iv) Delays in finalizing the procurement process, mainly due to the lengthy procurement process.
Summary of Chapters
Introduction: Provides the theoretical background on construction project management and the necessity of completing projects within agreed timeframes to ensure socio-economic development.
Methodology: Details the research approach, including a comprehensive literature review and interview surveys used to analyze project delays.
LITERATURE: Reviews previous global and local studies on the causes, effects, and management of delays in various construction sectors.
Overview of Harar Water Supply construction project: Describes the background, objectives, and scope of the Harar Water Supply and Sanitation Project.
Location of the Project and Duration: Defines the geographical setting, timeline, budget, and specific components of the project.
Purpose of the project: Outlines the primary intent to reduce water scarcity and sanitation issues in Harar while fostering health and awareness.
Project activity: Lists the specific physical and institutional activities undertaken during the project life cycle.
Assessment of the project achievement: Evaluates the outcomes based on quantified physical project outputs.
FINDING: Analyzes the specific implementation challenges, such as design complexity and procurement issues, and quantifies the delays and cost overruns.
CONCLUSIONSAND RECOMMENDATIONS: Synthesizes the research findings and provides recommendations for future infrastructure development projects.
Keywords
Construction delay, Harar Water Supply, Project management, Procurement process, Cost overrun, Implementation challenges, Water supply and sanitation, Infrastructure development, Design changes, Project sustainability, Socio-economic impact, Ethiopia, Public sector project.
Frequently Asked Questions
What is the primary objective of this research?
The study aims to identify and analyze the specific causes of construction delays in the Harar Water Supply and Sanitation Project and to examine potential solutions to improve future project management.
What are the core thematic areas covered in this work?
The work covers construction project management, the analysis of delay factors in public utility projects, procurement challenges, and the impact of design modifications on project timelines.
Which methodology does the author employ?
The author uses a detailed literature review to identify existing research on project delays, supplemented by an interview survey and a review of project completion reports for the Harar water supply project.
What does the main body of the text address?
The main body discusses theoretical perspectives on construction delays, provides an overview of the Harar project, documents specific implementation challenges, and compares actual project timelines and costs against original estimates.
What are the defining characteristics of this project?
The project is a major public sector initiative characterized by its complexity, reliance on foreign and capital funding, and the challenge of transporting water over long distances through challenging terrain.
Which key terms define this publication?
Key terms include construction delay, procurement, project management, Harar Water Supply, cost overrun, and infrastructure sustainability.
What specific implementation challenges were identified for the Harar project?
Significant challenges included frequent design changes, lack of close supervision, understaffing of the project team, heavy bureaucracy, and a lengthy, centralized procurement process.
How did the project address the identified delays?
The project management took corrective actions, such as establishing compensation and resettlement committees, adopting national financial systems, and adjusting tariffs to cover increased operational costs.
- Quote paper
- Barudin Abdi (Author), 2019, Causes for the delays in the construction of the Harar water supply project, Munich, GRIN Verlag, https://www.grin.com/document/456666