In a time of increasing requirements on construction projects, the simulation of construction processes in order to identify optimization potential of the execution becomes more and more important.
Apart from the needed information, the daily accurate acquisition of construction data is one main objective. In order to keep the acquisition effort as low as possible, it has to be clarified which data is really necessary for simulating the construction processes and which is not.
This work shall be a contribution to determine the appropriate level of detail that enables to reconstruct completely the execution of constructing highway bridge curbs.
Therefore different scenarios will be generated in which the availability of the respective data will be modified by generating process delays on purpose. By analyzing the effects of different process delays the importance of the investigated processes shall be determined in order to reduce the acquisition effort by optimizing the execution structure.
Inhaltsverzeichnis (Table of Contents)
- 1 INTRODUCTION
- 2 EXECUTION AND SIMULATION MODEL
- 3 THE SCENARIO ANALYSES
- 3.1 Scenario 1
- 3.2 Scenario 2
- 3.3 Scenario 3
- 3.4 Scenario 4
- 3.4.1 Case 1
- 3.4.2 Case 2
- 3.4.3 Case 3
- 3.4.4 Case 4
- 3.4.5 Case 5
- 4 OPTIMIZATION OF THE EXECUTION STRUCTURE
- 4.1 Comparison of the scenario results
- 4.2 Importance of the examined execution processes
- 4.3 Appropriate level of execution detail
- 4.3.1 Combination conditions
- 4.3.2 Potential process combinations
- 5 CONCLUSION
- 5.1 Results
- 5.2 Discussion
Zielsetzung und Themenschwerpunkte (Objectives and Key Themes)
This study aims to determine the appropriate level of detail for data acquisition in construction process simulation, focusing on building highway bridge curbs. It seeks to identify the essential data needed to accurately reconstruct the execution process and minimize the data acquisition effort through optimized execution structures.
- Data acquisition for construction process simulation
- Optimization of execution structures
- Impact of process delays on simulation accuracy
- Appropriate level of detail for data acquisition
- Minimization of data acquisition effort
Zusammenfassung der Kapitel (Chapter Summaries)
The first chapter provides an introduction to the research topic, highlighting the importance of accurate construction process simulation for optimizing project execution. It introduces the focus on constructing highway bridge curbs and the objective of identifying essential data for simulation.
Chapter 2 outlines the execution process of constructing bridge curbs, detailing the structure and specific characteristics of the chosen process. The implementation of the simulation model in Microsoft Office Project is explained, focusing on how process relationships and durations are represented in the model.
Chapter 3 examines different scenarios generated by intentionally introducing process delays, analyzing the effects of these delays on the overall execution. This analysis helps determine the importance of the investigated processes in terms of their impact on the final outcome.
Chapter 4 delves into potential possibilities for minimizing the execution structure to determine the appropriate level of detail for data acquisition. The analysis compares the results of the different scenarios and identifies the crucial processes that should be included in the simplified execution structure.
Schlüsselwörter (Keywords)
This study focuses on construction process simulation, data acquisition, execution optimization, highway bridge curbs, process delays, and the determination of an appropriate level of detail for data acquisition.
- Citation du texte
- M.Sc. Franziska Föhse (Auteur), 2011, Daily accurate data acquisition for simulation. Effects of different data scenarios, Munich, GRIN Verlag, https://www.grin.com/document/263250